Week # |
Dates |
Scheduled
activities |
Owner |
1 |
2-8
February |
Incorporate all proposals |
Eberlein |
1 |
2-8 February |
Complete RelaxNG-to-XSD transformation |
Kimber |
2 |
9-15
February |
Conduct small test review using DITAweb |
Review coordinator; Eberlein |
2 |
9-15 February |
archSpec: Edit of "Processing" completed (except
Keys) |
Eberlein |
2 |
9-15
February |
Initial edit of all new material completed |
Eberlein |
2 |
9-15 February |
Attribute rework for base & technicalContent
completed |
Anderson |
3 |
16-22
February |
Review #1 |
Review
coordinator |
4 |
23 February - March 1 |
Review #1 |
Review coordinator |
4 |
23
February - March 1 |
XML grammar files completed, tested and
available by March 1 |
Kimber |
5 |
2-8 March |
TC members and subcommittee begin using XML
grammar files and providing feedback |
|
5 |
2-8
March |
Prototype of "Contains/Contains by" completed |
Anderson |
6 |
9-15 March |
Process for generating "Contains/Contains by"
information completed |
Kimber |
7 |
16-22
March |
Key definition maps for LangRef added; @href
removed from navigation maps |
Anderson |
7 |
16-22 March |
"Contains/Contains by" content integrated into
spec |
Kimber |
7 |
16-22
March |
Style sheets & DITA-OT plug-ins updated |
Thomas |
7 |
16-22 March |
archSpec: Rework of Terminology & Keys
completed |
Eberlein |
7 |
16-22
March |
Incorporate "Spec clarifications and
improvements" |
|
8 |
23-29 March |
Review #2 |
Review coordinator |
9 |
30
March - 5 April |
Review #2 |
Review
coordinator |
10 |
6-12 April |
|
|
11 |
13-19
April |
archSpec: Rework of "Configuration,
specialization, and constraints" + "Non-normative" appendix
completed |
Eberlein |
11 |
13-19 April |
Attribute rework for learning & training
completed |
|
12 |
20-26
April |
Review #3 |
Review
coordinator |
13 |
27 April - 4 May |
Review #3 |
Review coordinator |
14 |
5-11
May |
|
|
15 |
12-18 May |
Final review |
Review coordinator |
16 |
19-25
May |
|
|
17 |
26 May - 1 June |
|
|