[Date Prev] | [Thread Prev] | [Thread Next] | [Date Next] -- [Date Index] | [Thread Index] | [List Home]
Subject: interop testing
[ notes from the interop discussion ] 1) new items - pre-finalisation of the specification proposals / updates 2) private testing - vendor to vendor (typically a month or so) 3) public testing - testing known to be occurring - summary results published 4) formal compliance testing - independent third party, branding, etc It is desirable to have a known release level at a known location for all the testing other than item 1). Currently the interop group has been performing 1) through 3). There have been some challenges with the vendor products mostly due to the compressed time schedule heading into the RSA conference and vendor extensions given the different vendor approaches and the uneven support amongst the server implementations. Tim.
[Date Prev] | [Thread Prev] | [Thread Next] | [Date Next] -- [Date Index] | [Thread Index] | [List Home]