Subject: ODF 1.0 Approved Errata 01 -- Public review comments


The public review period of our ODF 1.0 Approved Errata 01 document 
concluded on Friday.  We are required under OASIS TC Process 3.2 (
http://www.oasis-open.org/committees/process.php#publicReview) to take 
certain actions with regard to these comments:

"The TC must acknowledge the receipt of each comment, track the comments 
received, and publish to its primary e-mail list the disposition of each 
comment at the end of the review period."

I've gone through our public comment list and extracted the following 
comments which were submitted August 7th through August 22nd and which 
concerned the errata document. 

Dennis E. Hamilton:  
http://lists.oasis-open.org/archives/office-comment/200808/msg00012.html 
Sheldon Britton:  
http://lists.oasis-open.org/archives/office-comment/200808/msg00015.html
Dave Pawson: 
http://lists.oasis-open.org/archives/office-comment/200808/msg00017.html
Murata Mokoto: 
http://lists.oasis-open.org/archives/office-comment/200808/msg00027.html
Murata Mokoto: 
http://lists.oasis-open.org/archives/office-comment/200808/msg00052.html
Dennis E. Hamilton: 
http://lists.oasis-open.org/archives/office-comment/200808/msg00059.html

Let's see if we can get through these comments on Monday.  If we decide to 
change the approved errata draft, we can certainly do so, though it would 
require that we create and approve another draft and re-submit it for 
another day public review.  So any change will essentially delay 
publication by a month.  If we do not change the draft, we remain free to 
make additions or changes in 6 months, with an updated Approved Errata 
document. 

TC members should consider how they want to proceed:

Option #1 - We acknowledge  the public comments received, but decline to 
make any changes at this time.  This provides something to JTC1/SC34 now, 
but will delay any other comment resolutions by 6 months.

Option #2 -- We make changes suggested in the public comments, including 
expanding the scope to include the additional comments which Murata-san 
suggests are missing.  This will require preparation of a new draft, 
approval by the TC, and a new 15 day public review period.  So it will 
introduce an additional 1 month delay. 

Option #3 -- We make changes suggested in the public comments, but do not 
seek any further vote as Approved Errata.  So we essentially leave this 
draft Approved Errata document open, and can continue to add items to it. 
We make our intent know to not issue it as Approved Errata until we've 
caught up with the existing public comments, in particular all those from 
Murata-san.

Option #3 would get everything out faster if we could review and resolve 
all ODF 1.0 public comments in less than 6 months.  If we believe it would 
take more than 6 months to catch up, then Option #1 would be better. 
Option #2 gives as a smaller delay (1 month) but potentially allows us to 
address a few more comments.

-Rob