Folks,
This email is intended to start a discussion
regarding the schedule for the completion of the work of the
SCA Assembly TC.
Much though we love SCA and the discussions
that we are having in relation to the Assembly specification,
this is all being done in the context
of a goal - the publication of an OASIS standard. Now is a good time
to
discuss the schedule for completing
the work of publishing the SCA Assembly specification as an OASIS
standard.
List of milestones:
"No new issue"deadline (creation
of a high bar for raising any new issues)
Detailed Design for Testing complete
All issues resolved
All issues incorporated into specification
Testing commencement
1st Public Review
- Criteria for starting the 1st PR:
- a> close all the open issues (unresolved
issues may be closed by deferring to future release)
- b> include conformance statements
(required by OASIS TC process)
Testing completion
Issues from PR and testing resolved
Issues from PR and testing incorporated
2nd Public Review
Issues from PR2 and testing resolved
Issues from PR2 and testing incorporated
Possible - another round of updates
to specs and 3rd Public Review
Committee spec
OASIS standard
A potential schedule for these various
milestones is as follows, bearing in mind various
OASIS-mandatory aspects required for
Public Reviews:
Sep 15, 2008
- "No new issue"deadline
Nov 15, 2008
- Detailed Design for Testing complete
Dec 19 2008 -
All issues resolved
Jan 13 2009 -
All issues incorporated into specification
Jan 20 2009
- Testing commencement
Jan 23, 2009
- 1st Public Review starts (60 day)
Mar 24, 2009
- 1st Public Review completes
Mar 24 2009
- Testing completion
Apr 21 2009
- Issues from PR and testing resolved
Apr 28 2009
- Issues from PR and testing incorporated
May 1 2009
- 2nd public review starts(15 day)
May 18 2009
- 2nd public review completes
May 26 2009
- Issues from PR2 and testing resolved
May 31 2009
- Issues from PR2 and testing incorporated
May 31, 2009
- Finish all the work
July 4, 2008
- Submit specs to OASIS for OS vote
Straightforward really - just a small
matter of work ;-)
Views and discussion welcome.
Yours, Mike.
Strategist - Emerging Technologies, SCA & SDO.
Co Chair OASIS SCA Assembly TC.
IBM Hursley Park, Mail Point 146, Winchester, SO21 2JN, Great Britain.
Phone & FAX: +44-1962-818014 Mobile: +44-7802-467431
Email: mike_edwards@uk.ibm.com
Unless stated otherwise above:
IBM United Kingdom Limited - Registered in England and Wales with number
741598.