OASIS Mailing List ArchivesView the OASIS mailing list archive below
or browse/search using MarkMail.

 


Help: OASIS Mailing Lists Help | MarkMail Help

ubl message

[Date Prev] | [Thread Prev] | [Thread Next] | [Date Next] -- [Date Index] | [Thread Index] | [List Home]


Subject: Re: [ubl-psc] Urgent PSC Call Needed


Title: Re: [ubl-psc] Urgent PSC Call Needed
Tim

As you know I was ‘Out of UBL’ for a few weeks there, so I’m not sure what you mean by ‘the changes already flagged in the previous review’.  All I do know is that I won’t have incorporated them because all I was asked to do by Peter was to go through all of the spreadsheets checking the English, the grammar (which varies so greatly that I’m only changing it where it impedes the sense) and the correctness of description.

I have done this for most of the common library (done to the end of Shipment Stage) but the changes are not highlighted; for the remainder of the common library and the document spreadsheets I will leave the highlights in place (in yellow) so everyone can see the proposed changes.  The only really significant changes (above Shipment Stage) have been the descriptions in Reminder Line which previously described about everything except a Reminder Line.

Where I think there is still an issue, I will highlight in red.

With regard the the meeting tomorrow, I think it should be OK as the queuing starts at 08:30, so let’s stick to that time.

I also have some other issues resulting from the convergence work that I want to discuss during the public review time.  These are (reading from my scribbles and not checking them in detail):
  1. In Credit and Debit Note, there is an Order Reference in the Header, but no Line Reference in the Line
  2. In Debit Note, Monetary Total is qualified by ‘Requested’ - why ?
  3. do we need a PayerParty to balance PayeeParty (customer side / supplier side) ?
  4. Why all the Parties in Remittance Advice Line ?
  5. Why are Contact and Person 0..1 in Party ?
  6. What is the meaning of the TaxLevelCode in Tax Scheme ?
  7. Do we really need a Tax Category Name BBIE ?
  8. Explain how Tax Tiering works.
  9. ID in Payment.Reference is confusing; reference to actual payment made should be InstructionID as per the Core Component.
  10. Do we need Payment Means in Order ? e.g. to say ‘I intent to pay for this Order with a Purchasing Card / by cash


Regards, M


Mark Leitch
Director - Tritorr Ltd
tel.:       +44 1932 821112
cell.:      +44 7881 822999
mail:      ml@tritorr.com
skype:    wmarkle
site:       www.tritorr.com



From: Tim McGrath <tmcgrath@portcomm.com.au>
Date: Tue, 26 Sep 2006 16:58:52 +0800
To: Mark Leitch <ml@tritorr.com>
Cc: <swebb@gefeg.com>, <ubl-psc@lists.oasis-open.org>, "'ubl@lists.oasis-open.org'" <ubl@lists.oasis-open.org>
Subject: Re: [ubl-psc] Urgent PSC Call Needed

on behalf of sylvia - who is hopefully asleep, i can add that the TC wanted to have some other eyeballs to review these edits before they were caste into stone as part of the schemas.  we saw a canference call as an efficient way of running through what you propose and signing off.

so it would be less value to have a call without you. if sylvia's time is inconvenient then can you propose another.  

we need to conclude this in the next few days if we want the changes to go into the final package.

also, i am assuming you have also incorporated the changes already flagged in the previous review.

the UBL/TBG1 report is useful because we would all appreciate this perspective going into the CEFACT Forum.  Unfortunately I cannot attend but Sylvia will be there (albeit with her TBG6 hat on).  It would be useful to talk over the differences in approach before you get to New Delhi.


Mark Leitch wrote:
Re: [ubl-psc] Urgent PSC Call Needed Sylvia
 
The spreadsheets I am working on are the PRD3 final spreadsheets.  I hope to finish the work today.
 
Vis-à-vis the convergence work with TBG1, I am happy to report that we are on target with the plan and that we have completed mapping the Invoice, Credit Note, Debit Note and Remittance Advice but for a few issues of a structural nature.  We are now working together with a good level of understanding and purpose.
 
In summary, the issues relate to the use of core components and the assembly of documents from the same.  Whereas we have adopted a “library’ approach (where we need a BBIE in a document, we bring it to the document in the context of its ABIE using an association), TBG1 have gone for a “picking” approach which brings the BBIE to the document without its neighbours in the ABIE.  Neither of us have any overwhelming advice that either of these approaches is the correct one and we will need some urgent advice on these issues from the relevant UN/CEFACT groups for the convergence work to produce a unified standard of implementable substance.
 
In the meantime, we will continue with the convergence work and hold the results in abeyance for the official UN/CEFACT direction on core component use and message assembly.
 
I’m sure that Martin will be able to go into some detailed examples to illustrate these points at the meeting tomorrow.  I will try to attend, but can’t guarantee that I won’t still be in the visa queue at the Indian High Commission in London.
 
I haven’t seen any minutes for the Pacific call you refer to.  Please can you let me know what questions were raised and I will comment where I can.
 
Regards, Mark
 
Mark Leitch
 
Director - Tritorr Ltd
 
tel.:       +44 1932 821112
cell.:      +44 7881 822999
mail:      ml@tritorr.com
skype:    wmarkle
site:       www.tritorr.com <http://www.tritorr.com>
 

 > From: Sylvia Webb <swebb@gefeg.com> <mailto:swebb@gefeg.com>
> Organization: GEFEG
> Reply-To: <swebb@gefeg.com> <mailto:swebb@gefeg.com>
> Date: Mon, 25 Sep 2006 23:44:43 -0700
> To: <ubl-psc@lists.oasis-open.org> <mailto:ubl-psc@lists.oasis-open.org> , 'Tim McGrath' <tmcgrath@portcomm.com.au> <mailto:tmcgrath@portcomm.com.au>
> Subject: [ubl-psc] Urgent PSC Call Needed
>
> All,
>  
> We must have a PSC call to answer questions that were asked in the Pacific
> call today and to review the work that is being done to make editorial
> changes to the spreadsheets.
>  
> A call is scheduled for Wednesday, 27 September at 16:00 CET/10:00 AM EDT.
> This is one hour before the regularly scheduled UBL TC Atlantic call.
> Additional requests from the Pacific call include:
>  
>  
>  
>  
>
> * Peter, please confirm that the spreadsheets that you provided to
> Mark Leitch are from the PRD3 release package.
> * Mark, please send a status report of last week's UBL/TBG1 meetings
> to the UBL TC list.
>
> If you aren't available at this time, please send other times you are
> available on Wednesday.  
>  
>  
> Regards,
> Sylvia
>
>
>
>
 

--
regards
tim mcgrath
phone: +618 93352228  
postal: po box 1289   fremantle    western australia 6160
web: http://www.portcomm.com.au/tmcgrath



[Date Prev] | [Thread Prev] | [Thread Next] | [Date Next] -- [Date Index] | [Thread Index] | [List Home]