Subject: RE: [amqp] RE: Timeline leading up to approval of Committee Specification Draft


Please copy the public review notice to:

dev@qpid.apache.org

 

Thanks,

-Steve

 

From: amqp@lists.oasis-open.org [mailto:amqp@lists.oasis-open.org] On Behalf Of Ram Jeyaraman
Sent: Thursday, February 16, 2012 3:23 PM
To: amqp@lists.oasis-open.org
Cc: Angus R Telfer (art@inetco.com)
Subject: [amqp] RE: Timeline leading up to approval of Committee Specification Draft

 

Ø  Feb 21st

o   Assuming everything goes well, TC is expected to close the remaining two open issues (AMQP-58 and AMQP-59) and approve CSD and CSPRD.

o   Following approval, Chairs will work with TC admin to initiate public review. The public review is expected to begin in about 2 weeks following the CSD approval.

 

Notification of the public review will be sent by the TC admin to the OASIS Membership list (which is public).  In addition, if you want to include any external parties in the public review notification, please provide them (on this thread).

 

Thanks.

 

From: Ram Jeyaraman
Sent: Tuesday, February 14, 2012 5:00 PM
To: amqp@lists.oasis-open.org
Subject: Timeline leading up to approval of Committee Specification Draft

 

As we discussed during the TC meeting  today, here is the timeline leading up to approval of Committee Specification Draft of the specification:

·         Feb 14

o   Chairs will provide instructions to the editors to prepare the CSD (Committee Specification Draft) and CSDPRD (Committee Specification Public Review Draft) packages [DONE].

·         No later than Feb 17th

o   Editors will upload the CSD and CSDPRD packages to the TC document repository.

o   Chairs will post to the TC mailing list the text of the CSD and CSPRD approval motion.

·         Feb 17th through Feb 20th

o   Review the CSD and CSDPRD packages with OASIS TC administrator (Chet).

·         Feb 21st

o   Assuming everything goes well, TC is expected to close the remaining two open issues (AMQP-58 and AMQP-59) and approve CSD and CSPRD.

o   Following approval, Chairs will work with TC admin to initiate public review. The public review is expected to begin in about 2 weeks following the CSD approval.

 

Any questions on the timeline?

 