Thanks, JoAnn. I'll add the deadlines
to the proposals in the Trello board.
Best,
Kris
Kristen James Eberlein
Principal consultant, Eberlein Consulting
Co-chair, OASIS DITA Technical Committee
Charter member, OASIS DITA Adoption Committee
www.eberleinconsulting.com
+1 919 682-2290; kriseberlein (skype)
On 2/25/2013 10:23 AM, JoAnn Hackos wrote:
JoAnn T. Hackos, PhD
President
Comtech Services Inc.
710 Kipling Street, Suite 400
Denver, CO 80215
303-232-7586
When the SC is done with the
proposals, you'll want to get them to the TC reviewers and
begin the back and forth so that you can make the
necessary changes before submitting the proposals to the
TC. Here is a list of the TC that volunteered to serve as
reviewers for the proposals:
- Eliot Kimber
- Stan Doherty
- Kris Eberlein
- Thilo Bucholtz
So, if you all can go ahead and build deadlines for
when you expect the proposals to make it to the TC, I'd
really appreciate it. I'm including the following table
to help with the deadline setting.
Item
|
Deadline
|
Comments
|
New topic for
archSpec |
Week of Feb
25-March 1
|
|
SC reviews
stage-3 proposals |
SC meeting on March 4
|
|
Revisions to
stage-3 proposals, based on feedback from SC
|
SC edits by March 6 |
|
TC reviewers
review stage-3 proposals |
Reviewers start March 7 — March 21 |
Allow a week
or more for this |
Revise
stage-3 proposals based on feedback from
reviewers |
March 21 - 28 |
Allow a week
or more for this |
Stage-3
proposals submitted to TC
|
March 29 |
|
I appreciate the good work that
the SC is doing; you all have a larger percentage of
proposals moving steadily through the process than
anyone else.
Best,
Kris
Kristen James Eberlein
Principal consultant, Eberlein Consulting
Co-chair, OASIS DITA Technical Committee
Charter member, OASIS DITA Adoption Committee
www.eberleinconsulting.com
+1 919 682-2290; kriseberlein (skype)
On 2/25/2013 9:08 AM, JoAnn Hackos wrote:
Kris,
I expect Seth to conduct the SC vote on Bob's proposals
next week. I'm one of the reviewers and I have completed
my review. I have also nearly completed the topic for
the arch spec and will also have that ready for review
next week.
Again, please members, review Bob's proposals. You
have plenty of time.
We are still waiting for Priestley on 13097. Seth
needs for respond on 13102. I don't think there has been
any progress.
We do need to ask the reviewers to complete their
reviews, although I'm one of them and I've completed
mine.
JoAnn
Sent from my iPad
JoAnn Hackos
Comtech Services Inc
710 Kipling Street Suite 400
Lakewood CO 80215
Folks, I need you to
assign deadlines for the following proposals. I
understand that #13097 is dependent on #13121, for
which Michael Priestley has given a deadline of
March 15.
Does the subcommittee still intend on moving forward
on #13102 for the DITA 1.3 release, or do you want
to defer that to a future release of DITA?
Proposal # |
Owner |
Description |
Stage |
Comments |
13086 |
TechComm SC |
Add troubleshooting element to
<step> |
3 |
|
13096 |
TechComm SC |
Add troubleshooting section to
<task> |
3 |
|
13097 |
TechComm SC |
Troubleshooting topic |
2 |
|
13098 |
TechComm SC |
Add new troubleshooting value to
@type attribute for <note> |
3 |
|
13102 |
TechComm SC |
Revision history/release
management markup |
2 |
|
Best,
Kris
Kristen James Eberlein
Principal consultant, Eberlein Consulting
Co-chair, OASIS DITA Technical Committee
Charter member, OASIS DITA Adoption Committee
www.eberleinconsulting.com
+1 919 682-2290; kriseberlein (skype)
On 2/18/2013 12:19 PM, Kristen James Eberlein wrote:
OK, then a tentative
deadline for when the DITA TC will see
proposals #13086, 13096, and
13098 would be helpful.
Here are some thoughts about the next moves that
might be helpful in planning the deadline.
Item
|
Deadline
|
Comments
|
New
topic for archSpec |
Week
of Feb 25-March 1
|
|
SC
reviews stage-3 proposals |
SC meeting on March 4?
March 18?
|
|
Revisions
to stage-3 proposals, based on feedback
from SC
|
|
|
TC
reviewers review stage-3 proposals |
|
Allow
a week or more for this |
Revise
stage-3 proposals based on feedback from
reviewers |
|
Allow
a week or more for this |
Stage-3
proposals submitted to TC
|
|
|
Best,
Kris
Kristen James Eberlein
Principal consultant, Eberlein Consulting
Co-chair, OASIS DITA Technical Committee
Charter member, OASIS DITA Adoption Committee
www.eberleinconsulting.com
+1 919 682-2290; kriseberlein (skype)
On 2/18/2013 10:24 AM, JoAnn Hackos wrote:
Kris,
Our Sta
GE 3 proposals of 13086 13096 13098 are ready
except for the new topic for the arch spec
explaining the relationships among the three
options for troubleshooting. Our proposal for
troubleshooting topic has been waiting for
Michael Priestly's proposal for the steps
domain. He has made no progress on that as far
as I know. Seth Park has made to progress that I
know of on release management. I haven't checked
on 13121 at this time to see what it is but just
creating a steps domain will not complete the
troubleshooting topic proposal.
I hope to write the new topic the
troubleshooting sometime in the next week. I
just reviewed Bob's stage 3 proposals and feel
they are complete.
JoAnn
Sent from my iPad
JoAnn Hackos
Comtech Services Inc
710 Kipling Street Suite 400
Lakewood CO 80215
Dear members of
the TechComm subcommittee:
I am contacting all individuals and
subcommittees that have more than two
proposals in the process for DITA 1.3.
Below is a list of the proposals advanced
by the subcommittee:
Proposal # |
Owner |
Description |
Stage |
Comments |
|
|
13086 |
TechComm SC |
Add troubleshooting
element to <step> |
3 |
|
|
|
13096 |
TechComm SC |
Add troubleshooting
section to <task> |
3 |
|
|
|
13097 |
TechComm SC |
Troubleshooting topic |
2 |
|
|
|
13098 |
TechComm SC |
New troubleshooting
<note> type |
3 |
|
|
|
13102 |
TechComm SC |
Revision history/release
management markup |
2 |
|
|
|
13113 |
TechComm SC |
Make <steps>
available in troubleshooting topic |
2 |
Hopefully
handled by #13121 |
I'd like the SC to
provide the following information:
- Tentative date
for when you think you will have the
stage-3 proposals for proposals
#13086, 13096, and 13098 ready.
- Whether you
plan to have the stage-3 proposals
for
#13086, 13096,
and 13098 ready at the same time.
Because of the questions previously
posed by the TC and the content
overlap, this might be a sensible
approach.
- An assessment
of whether you think you will be
advancing a stage-2 proposal for
#13102.
I'm leaving
#13097 out of this discussion, since
it has a current dependency on
proposal #13121. Ditto for #13113,
which is really a placeholder for a
less-favored implementation approach
if #13121 does not materialize.
Best,
Kris
Kristen James Eberlein
Principal consultant, Eberlein
Consulting
Co-chair, OASIS DITA Technical Committee
Charter member, OASIS DITA Adoption
Committee
www.eberleinconsulting.com
+1 919 682-2290; kriseberlein (skype)
---------------------------------------------------------------------
To unsubscribe from this mail list, you must
leave the OASIS TC that generates this mail.
Follow this link to all your TCs in OASIS at:
https://www.oasis-open.org/apps/org/workgroup/portal/my_workgroups.php
---------------------------------------------------------------------
To unsubscribe from this mail list, you must leave
the OASIS TC that generates this mail. Follow this
link to all your TCs in OASIS at:
https://www.oasis-open.org/apps/org/workgroup/portal/my_workgroups.php
---------------------------------------------------------------------
To unsubscribe from this mail list, you must leave the
OASIS TC that generates this mail. Follow this link to
all your TCs in OASIS at:
https://www.oasis-open.org/apps/org/workgroup/portal/my_workgroups.php
---------------------------------------------------------------------
To unsubscribe from this mail list, you must leave the OASIS
TC that generates this mail. Follow this link to all your
TCs in OASIS at:
https://www.oasis-open.org/apps/org/workgroup/portal/my_workgroups.php
|