OASIS Mailing List ArchivesView the OASIS mailing list archive below
or browse/search using MarkMail.

 


Help: OASIS Mailing Lists Help | MarkMail Help

regrep-cc-review message

[Date Prev] | [Thread Prev] | [Thread Next] | [Date Next] -- [Date Index] | [Thread Index] | [List Home]


Subject: CC Review Revised Workplan


Team,

Now that I have a good sense of our pace, I'd like to present a reviews
workplan (please see attached). You'll recall that the original workplan
was based on our creating an XML serialization for Core Components,
which is no longer the case.

Highlights are as follows (I included some padding for summer vacations
and Labor Day):

- Our "Core Components RIM Binding" Technical Note will essentially be
completed on 09/15/03 - what follows that are finishing touches
(editing), and the Registry TC vote;

- Our "Verification Results" document for is scheduled to be sent to the
CCTS Team on 09/19/03;

- The Registry TC vote on the Technical Note is scheduled to complete on
09/26/03;

At the top I've listed a "general flow" without the dates.

Please review and provide feedback - I'd like to make our Verification
Test "official" to the UN/CEFACT CCTS Team this coming Monday
(06/30/03).

Thanks!
Joe

Core Components Workplan.doc

begin:vcard 
n:Chiusano;Joseph
tel;work:(703) 902-6923
x-mozilla-html:FALSE
url:www.bah.com
org:Booz | Allen | Hamilton;IT Digital Strategies Team
adr:;;8283 Greensboro Drive;McLean;VA;22012;
version:2.1
email;internet:chiusano_joseph@bah.com
title:Senior Consultant
fn:Joseph M. Chiusano
end:vcard


[Date Prev] | [Thread Prev] | [Thread Next] | [Date Next] -- [Date Index] | [Thread Index] | [List Home]