Subject: Proposed SCA schedule



For now this message is informational...

At the last Liaison committee meeting a proposal for an overall schedule for completing the 1.1 SCA specs was discussed.  The highlights are:

Tentative dates for key milestones:
Sep 15, 2008 - Raise the bar for opening new issues (for all TCs)
Nov 15, 2008 - Detailed design for testing work
Jan 23, 2009 - Assembly TC to start 1st Public Review (60 day)
Feb 23, 2009 - Other TCs to start 1st Public Review (60 day)
May 31, 2009 - Finish all the work
July 4, 2008  - Submit specs to OASIS for OS vote


Some additional detail:
List of milestones:

"No new issue"deadline (creation of a high bar for raising any new issues)


Detailed Design for Testing complete

All issues resolved
All issues incorporated into specification


Testing commencement


1st Public Review
- Criteria for starting the 1st PR:

- a> close all the open issues (unresolved issues may be closed by deferring to future release)

- b> include conformance statements (required by OASIS TC process)


Testing completion
Issues from PR and testing resolved

Issues from PR and testing incorporated


2nd Public Review
Issues from PR2 and testing resolved

Issues from PR2 and testing incorporated


Possible - another round of updates to specs and 3rd Public Review


Committee spec
OASIS standard :


Dates proposed in Assembly TC:
A potential schedule for these various milestones is as follows, bearing in mind various
OASIS-mandatory aspects required for Public Reviews:


Sep 15, 2008         - "No new issue"deadline
Nov 15, 2008         - Detailed Design for Testing complete

Dec 19 2008        - All issues resolved
Jan 13 2009        - All issues incorporated into specification

Jan 20 2009         - Testing commencement


Jan 23, 2009         - 1st Public Review starts (60 day)
Mar 24, 2009         - 1st Public Review completes

Mar 24 2009         - Testing completion
Apr 21 2009         - Issues from PR and testing resolved

Apr 28 2009         - Issues from PR and testing incorporated


May 1 2009         - 2nd public review starts(15 day)
May 18 2009         - 2nd public review completes

May 26 2009         - Issues from PR2 and testing resolved

May 31 2009         - Issues from PR2 and testing incorporated


May 31, 2009         - Finish all the work
July 4, 2008          - Submit specs to OASIS for OS vote



Bryan Aupperle, Ph.D.
STSM, WebSphere Enterprise Platform Software Solution Architect
Master Inventor

Research Triangle Park,  NC
+1 919-254-7508 (T/L 444-7508)
Internet Address: aupperle@us.ibm.com


[Date Prev] | [Thread Prev] | [Thread Next] | [Date Next] -- [Date Index] | [Thread Index] | [List Home]