Subject: TX timeline strawhorse
Hi, Ian and I have spent some time roughing out what we believe might be a doable schedule for completing the WS-TX work. We are about halfway through the year and I think it will be important for us to complete our work in as close to the year timeframe as possible. Therefore as a general statement I would say we intend to lead the TC into a transition phase from "discovery" or raising issues into a phase of thinking about finalizing the specs. The interop events are a key part of this, and so we created the timeline more or less around these, and after a certain point trying to focus the TC effort on fixing problems identified during the interop. This draft timeline (below) is scheduled for discussion this Thursday - Agenda item 7. We look forward to your feedback, reaction, and help. Thanks, and talk with you then! Eric +1 781 902 8366 fax: +1 781 902 8009 blog: www.iona.com/blogs/newcomer Making Software Work Together (TM) --------------------- June 30: All non-interop-related C/AT/BA issues to be submitted to the TC. After this date the bar will be raised and the chairs will organize a ballot (orinary majority ballot) to accept any new non-interop-related issues. July 14: live endpoints for AT scenarios to become available Aug 18: AT interop testing complete. All interop-related C/AT issues to have been submitted to the TC. Work to resolve any issues. BA interop testing to start immediately after the completion of AT interop testing. Aug F2F (30/31): Approve WS-C, WS-AT public review (PR) drafts in order to start 60-day public review. Initiate public review process with TC Admin. Sep 4: Start 60 day PR for C/AT Sep 15: BA interop testing complete. All interop-related BA issues to Have hbeen submitted to the TC by this date. Work to resolve any issues. Oct 6: Produce/approve WS-BA public review (PR) drafts in order to start 60-day public review. Initiate public review process with TC Admin. Oct 13: Start 60 day PR for C/AT Nov 3: C/AT PR ends. Work to resolve any issues. [1] Nov 17: Produce/approve WS-C/AT PR report. Produce/approve committee Specs for C/AT. Nov ??: F2F (to be arranged) ?? Dec 13: WS-BA PR ends. Work to resolve any issues [2]. Jan 12: Produce/approve WS-BA PR report. Produce/approve committee specs for BA. Jan 15: Submit C/AT/BA committee specs to OASIS for OASIS standard ballot. Feb 1: OASIS to inform membership of forthcoming ballot Feb 16: Membership ballot starts. Feb 28: Voting period ends. All being well, we have an OASIS standard. [1], [2]. Any substantive changes made following the 60-day public Review require a further public review period of 15 days. This will move the schedule out.
[Date Prev] | [Thread Prev] | [Thread Next] | [Date Next] -- [Date Index] | [Thread Index] | [List Home]