For our discussion today, here is the
schedule we approved at the f2f last week as it was written on the board.
I've also transcribed it into a spreadsheet to make it easier to
track:
• Finish
issues 2-4 weeks Jan 31
• Incorporate
resolutions in draft 2-4 weeks Mar 1
• Approve
committee draft (inclusive of all normative changes from all issues) 2
weeks Mar 15
• Face
to face meeting to start editing cycle (end to end consistency, restructure)
5 days Mar 20-24
• Editing
complete for public review candidate 3 weeks (Public review candidate sent
for TC review) April 15
• Approve
public review candidate 2 weeks May 1
• Public
review 60 days June 30
– If
appropriate continue editing for improved readability
– Start
review and work on public comments as they are received
• Face
to face meeting to review/address public comments Week of July 17, 24 or
31
• Prepare
updated public review candidate 2 weeks Aug 1
• Second
public review cycle 15 days Aug 15
• Committee
spec Aug 30
• OASIS
Standard Oct. 15
• Note
dates are approximations some of which depend on OASIS process steps
or staff actions.
Also, please note that in addition to
those issues the issue list shows as ready for editing, we also 207, 216
and 226 at the f2f, so they are ready also.
.
Regards, Diane
IBM Emerging Internet Software Standards
drj@us.ibm.com
(919)254-7221 or 8-444-7221, Mobile: 919-624-5123, Fax 845-491-5709
Schedule jan 12 05.xls
[Date Prev]
| [Thread Prev]
| [Thread Next]
| [Date Next]
--
[Date Index]
| [Thread Index]
| [List Home]