Subject: RE: [virtio-comment] [RFC] virtio 1.3 schedule


Hi Cornelia, Michael,

> From: virtio-comment@lists.oasis-open.org <virtio-comment@lists.oasis-
> open.org> On Behalf Of Cornelia Huck
> Sent: Wednesday, April 12, 2023 12:17 PM

> >> - July 1st 2023: enter feature freeze; all proposed changes must at
> >>   least have an open github issue that refers to a proposal on-list
> >> - August 1st 2023: enter change freeze; everything needs to have been
> >>   voted upon (i.e. we can start with preparations for a release like
> >>   compiling the change log)
> >> - at the same time, fork virtio-next, which can be used for development
> >>   while we're working on the release
> >> - August/September 2023: prepare draft, initiate initial voting etc.
> >
> > Hmm looks like you forgot a 30 day the public review period (or is
> > that included in the "etc"? ).  During this period we will likely
> > receive review comments which we have to address. Should the changes
> > turn out to be material, another public review period will be required.
> > Let's spell it out please.
> 
> Yeah, that's what I meant with "etc"... let's make this:
> 
> - August 2023: prepare draft, aim to have it ready and voted upon by
>   August 31 the latest (preferrably earlier)
> - September 2023: public review period (30 days)
> - October 2023: another public review period, if needed; otherwise, get
>   comittee specification ready and voted upon
> - October (maybe November, if we're running late) 2023: virtio 1.3
>   released
> 
> The most important dates are feature freeze on Jul 1 and change freeze on Aug
> 1, I guess; for the rest, we depend on whether people are out on PTO, which
> kind of feedback we get, etc. -- but as long as we release
> 1.3 in 2023, I'll be happy enough.

We have two extension features that has gone through several reviews and are in advance stage (and also late) for 1.3. :)

1. inner hash v19, rolling to v20 anytime this week. 1 Patch.
[1] https://lists.oasis-open.org/archives/virtio-comment/202306/msg00490.html

2. first user of aq for legacy access at v7.
2 patches. First 2 are Fixes.
[2] https://lists.oasis-open.org/archives/virtio-comment/202306/msg00491.html

Both need few more days of review and vote.
Shall we please have few days in July for them so that it can be part of 1.3? 
or whole July is needed to prepare the draft spec?