Dear TC chairs,
The OpenCSA Steering Committee would like to get a status update for your TC. Please provide as much detailed information as possible for the following.
For each deliverable specification -
- What is the current status of the specification (CD, CS, PR, etc)?
- What is the remaining amount of work in terms of number of open issues, estimated time to resolve, etc?
- What is the status of testing (Test Assertions complete, Test Case complete, In PR, etc)?
- What is the estimated timeline of completing the testing work?
- Would this specification be included in the first batch to be released together as SCA v1.1?
- How many compliant implementations do you expect to become available before finalization of the specification? Which ones are they?
- Are there any concerns regarding the completion of the spec work which the SC should be aware of and can help with?
- Are there any issues that require coordination with the other TCs via the Liaison Subcommittee?
Thank you for your time!
Sanjay